Projects under Implementation

vReconstruction of Alwastiti  hospital

Cost of the project:3778491000

The beneficiary :ministry of health

Duration of the project:1127

pursuit date:19/8/2004

Proportion OF Achievement :98% . 

vAlwasit presidency Building
1. Cost: 2052919000 dinars
2nd The beneficiary : the Ministry of Higher Education and Scientific Research.
The current work:
the completion of the earthy excavation, carrying out work of burial with mixed gravel,& the completion of pouring foundations and continuing work of iron for foundation.
- Project description:
Building consisting of 3 single-stories floor area of 3900 m2 and the building for the departments and the Department of the Presidency of the University

 

vprojectof classrooms and galleries (the concrete structure) / University of Alnahrain.
- Cost: 3445000000 dinars (three billion and four hundred and five and forty million dinars)
- Project Duration: 300 days
- History Direct: 1-9 / 2008
- Execution rate: 35%
- The current work:

 the completion of the earthy excavation, carrying out work of  burial with mixed gravel, the completion of pouring foundations and columns of the ground floor, the current work of the mold and reinforcing iron to the remaining columns, roof and floor
- Project description:
Consists of a two-stories'  building, the area of one floor is 8100 m2 and includes 2 classrooms and galleries and halls  for management .
building project presidency of Alnahrain .
- Cost: 7915000000 dinars (seven billion, nine hundred and five and ten million dinars)
- Duration of the project: 780 on
- History Direct: 9-11 / 2008
- The current execution rate: 10%
-
 student club  project,/ the University of Alnahrain .
- Cost: 5300000000 dinars (five billion three hundred million)
- Duration of the project: 540 days "
- Execution rate: 7%
- History Direct: 12-22-2008
- The current work:

the completion of the excavation dirt, continuing to work of mattress with mixed gravel under the foundations.
- Project description: consists of a two-stories building floor area per 4600 m2.

 